Type of scheduling in which the operations of an order are scheduled backwards starting from the order due date.
The scheduled start and scheduled finish of the order are determined via this scheduling type.
Scheduling type for networks, in which the latest start and finish dates for the activities are calculated backwards, starting from the basic finish date. The system then starts at the latest start date for the network and calculates the earliest start and finish dates forwards.