Show TOC
Define
Parameters for WBS Scheduling
The profile for WBS
scheduling, for example, contains the following control
parameters:
scheduling type
- whether the dates are to be recalculated
automatically when saving
- whether the error log is displayed
automatically if errors were determined during scheduling
- the number of days the start may be in the
past
- whether basic dates are to be adapted if the
earliest or latest dates of the network change
- maximum reduction level for
reduction
The profile for WBS scheduling is stored in the
project profile.
Standard
Settings
Control parameters for WBS scheduling are
available in the standard SAP R/3 System.
Activities
1. Define the
control parameters.
2. Enter the
profile in the project profile.