Parameters for Network Scheduling
In this step you define control parameters for
scheduling depending on the plant, the type of network and the production
scheduler, for example:
- whether basic dates are to be adjusted if the
network is shifted within the earliest/latest dates
- whether or how many days the start date can be
in the past
- whether the dates are to be automatically
recalculated on saving
- whether the error log is automatically
displayed if errors were calculated in scheduling
- the number of days that the start date is in
the past
- the reduction type that defines whether all
the operations should be reduced or only those on the critical
path
- maximum reduction level for
reduction
Standard
Settings
Control parameters are saved for scheduling in
the standard SAP package.
Activities
Define the control parameters.