The order report appears. In the case of a sales order, the sales order number and the accompanying procurement proposals are displayed. In the case of a planned order and a production order the corresponding order number is displayed.
The receipt elements are highlighted in color. Thus, you can recognize whether problem situations exist for the lower BOM levels. You can check the significance of the colors by selecting View

If you have not entered an item number for a sales order, a list of all items for the sales order now appears. Select the one that you require.

You can access the order report directly from the MRP list or the stock/requirements list, by positioning the cursor on the required MRP element and choosing
.
Function |
How to call up function |
What you should know |
Display only receipt elements that have an exception situation |
|
The system displays an overview of all BOM levels where date and quantity problems exist. |
Display all receipt elements |
|
The system displays an overview of all BOM levels where receipt elements are scheduled. |
Display only the BOM level directly below the order level. |
Click on the receipt element |
|
Display the long text for the exception message |
Click on the exception message number |
The system displays the long text for the exception message in the status line. |
Access stock/requirements list for component |
Position the cursor on the component and choose Details ® Stock/requirements |
|
Display and change MRP element |
|
|
Convert MRP element |
corresponding function under Details |
|
Access material memo |
|
|
Access graphic |
|
A network graphic appears in a separate window. You can shrink or enlarge the graphic, access screens for processing individual MRP elements, print the graphic and so on. |
Display receipt elements in total quantity or required quantity |
Edit ® Complete receipt quantities or Quantity needed |
The display differentiates
Example: An order is scheduled for 50 pieces. As the components are frequently used, a dependent requirement from another material for 50 pieces is added. Therefore, 100 pieces in total must be available for this BOM level. Check for required quantity: a warehouse stock of 50 pieces would be sufficient. The system would indicate that there are no problems on this particular BOM level. Check for complete receipts quantity: the total quantity would have to be in stock or scheduled, so that the system could indicate that there are no problems on this particular BOM level. |