Define Order Value Updating for Orders for Projects

In this step, you stipulate how the system records the planned costs for orders assigned to projects.

Orders can be apportioned or appended.

The plan value of the order is added to the committed value of the corresponding WBS element.
The plan value of the order is added to the plan value of the corresponding WBS element.

As a rule, the following applies:

You can specify with the appended indicator how the plan values of the order are included in the planning value of the respective WBS element for combinations of the following:

The following applies to the indicators:

The plan value of the order is added to the plan value of the WBS element. The total is displayed as the project plan value in the information system.
The plan value of the order is not added to the plan value of the WBS element.
The plan value of the order is added to the committed value of the WBS element as soon as the order has status "created".
The plan value of the order is added to the committed value of the WBS element only once the order has status "released".

Exception:

Plan values from networks used for planning are not added to the committed value of the WBS element. The network type specifies whether a network is used for planning.

Additional information about network type