Show TOC

Activate Project Cash Management in company code

In this step, you activate Project Cash Management for particular company codes. If you have assigned a number of company codes to one FM area, you have the option of activating some of these company codes, while leaving others inactive.

Requirements

Before you can activate Project Cash Management for a company code, the following conditions must be met:

Activity

Select the company codes which you want to activate, and save the table entries.

&ADDITIONAL HINTS&