You use the alert monitor of the Computing Center Management System (CCMS) for PI to monitor the following components:
● Business Process Engine
The Business Process Engine is responsible for executing and persisting integration processes. For more information about integration processes, see Designing Cross-Component Integration Processes.
If the tree element for the Business Process Engine is green, you do not need to take any further action.
If the tree element is red, the tree structure contains at least one red element (attribute), which indicates an error. Navigate to the attribute and double-click the error short text. The system displays a long text containing detailed information about the cause of the error and how to correct it. You can use Properties to define an auto-reaction method for each attribute.