Task Sequence 
You use this function to determine the sequence of tasks in which they are executed in the consolidation monitor.
The sequence of tasks is dependent on the consolidation area: Each consolidation area can have only one task hierarchy and, therefore, only one sequence of tasks.
You have already defined the tasks to be used in the task sequence and inserted them in the task hierarchy.
The system enforces a required sequence of certain tasks, thereby creating an initial, raw structure of tasks. This ensures that these tasks are executed in the correct sequence as required by the system and/or accounting rules.
Internally, the tasks are divided into several blocks. The numbers of these blocks dictate the required sequence. A set of tasks belonging to any given block can be executed in any order.
The following table illustrates the internal blocks and their tasks:
Block |
Task |
1 |
Balance carryforward |
2 |
Period initialization |
|
Custom task |
3 |
Data collection |
|
Copy task |
|
Validation of reported financial data |
|
Custom task |
4 |
Data collection of additional financial data for consolidation of investments |
|
Copy task |
|
Validation of reported financial data |
|
Currency translation |
|
Reconciliations |
|
Manual postings |
|
Reclassification |
|
Allocation |
|
Custom task |
5 |
Data collection of additional financial data for consolidation of investments |
|
Copy task |
|
Currency translation |
|
Manual postings |
|
Preparation for change of consolidation group |
|
Validation of reported financial data |
|
Reclassification |
|
Allocation |
|
Custom task |
6 |
Data collection of additional financial data for consolidation of investments |
|
Currency translation |
|
Preparation for change of consolidation group |
|
Manual postings (in group currency) |
|
Validation of reported financial data (in group currency) |
|
Reclassification (in group currency) |
|
Allocation (in group currency) |
|
Custom task |
7 |
Data collection of additional financial data for consolidation of investments |
|
Validation of reported financial data (in group currency) |
|
Reclassification (in group currency) |
|
Allocation (in group currency) |
|
Custom task |
8 |
Data collection of additional financial data for consolidation of investments |
|
Validation of standardized financial data |
|
Custom task |
9 |
Preparation for change of consolidation group |
|
Validation of standardized financial data |
|
Data collection of additional financial data for consolidation of investments |
|
Manual postings (in group currency) |
|
Interunit elimination |
|
Elimination of IU profit/loss in transferred inventory |
|
Consolidation of investments |
|
Posting of group shares |
|
Reclassification |
|
Allocation |
|
Custom task |
10 |
Validation of consolidated financial data |
|
Custom task |

The collection of reported financial data must be complete before you can translate the (standardized) data into group currency.
Blocks can have multiple occurrences of certain tasks (for example, tasks for manual posting, reclassification, and allocation). Multiple tasks are distinguished by their document types.
For accounting or organizational reasons you may want to determine a sequence of tasks within a block. Therefore, Customizing lets you determine a required sequence at this deeper level.
If a second task absolutely depends on the results of a first task, you can assign the first task as the preceding task to the second task.

If you want to standardize the reported financial data to meet corporate policy, you can decide whether a given task is to be run before or after currency translation.
You can assign two preceding tasks to a task, which then executes the two preceding tasks in parallel.


Also compare the example shown later.
The following conditions must be met when you define the task sequence.
· You need to adhere to the required sequence.
· You can assign only one balance carryforward task per task hierarchy.
· Each document type you use can only occur once within a task group. However, there is an exception: The same document type can be used by the reconciliation task and its associated task for interunit elimination.
· Recursions of tasks are not allowed in the task sequence – that is, multiple tasks may not point to each other. This can happen if the first task is defined (directly or indirectly) as the preceding task of the second task, and the second task is defined as the preceding task of the first task.

The following task definition is not permitted:

To make the customizing settings for the sequence of tasks, proceed as follows:
...
1. To determine the individual task sequence, go to the process view of the workbench and choose Consolidation Monitor ® Task.
2.
Modify the task
hierarchy to meet your requirements. To structure the tasks, you can combine
tasks in task
groups
(which represent nodes in the hierarchy). You
can then refer to the task groups in the consolidation monitor (for example,
to display them in columns and for summarizing the tasks for the task status
display).
Save the changes.
The system uses this sequence for the definition of preceding tasks.
3. To determine preceding tasks, go to the process view of the workbench and choose Consolidation Monitor ® Task Sequence.
Run Task Sequence in change mode.
The work area of the workbench shows the task sequence as previously defined in the task hierarchy.
4. In the hierarchy, select the task that is the preceding task. Then Drag&Drop it to the task it precedes.
Save your changes.
If the task sequence meets the conditions mentioned earlier, then the system inserts the preceding task. If a condition is not met, an error message is displayed.
The task sequence is reflected in the display of the tasks and in the status management in the consolidation monitor.

Once you have started executing the consolidation process for a period, you should no longer modify the underlying sequence of tasks.
Here is an example of a possible sequence of tasks.
The symbols have the following meanings:
- at
the top level: Consolidation area
- at
the second level: Task without a preceding task
- Task
with a preceding task
-
Preceding task
Tasks |
Description |
|
Consolidation area |
|
Balance carryforward |
|
Data entry task 1 |
|
Balance carryforward (precedes data entry task 1) |
|
Data entry task 2 |
|
Balance carryforward |
|
Validation of reported financial data |
|
Data entry task 1 |
|
Data entry task 2 |
|
Reclassifications for consolidation units |
|
Manual standardizing entries |
|
Reclassifications for consolidation units |
|
Currency translation |
|
Validation of standardized financial data |
|
Elimination of IU payables and receivables |
|
Elimination of IU revenue and expense |
|
Elimination of investment income |
|
Elimination of IU profit/loss in transferred inventory |
|
Consolidation of investments |
|
Manual consolidation of investments |
|
Reclassifications for consolidation groups |
|
Manual consolidation of investments |
|
Manual reclassifications for consolidation groups |
|
Validation of consolidated financial data |
|
Manual reclassifications for consolidation groups |