This graphic is explained in the accompanying text Cost Centers (Detail): Actual/Plan Situation Formatted (SCR) Locate the document in its SAP Library structure

Use

This crystal report provides an overview by cost element of the actual and planned costs incurred on a cost center for the current fiscal year, cumulated up to the current fiscal year, and projected based on the cumulated actual costs.

Structure

The workbook contains the following query:

Technical Name of Query

Name and Short Description

0CCA_C11_Q0002_CR

Cost Center (Detail): Actual/Plan Situation Formatted

 

 