      Creating the Project in the Project Builder
      Using Relationships to Link Activities
      Planning the Output and Duration of Activities
      Scheduling the Project
      Planning Costs
      Allocating the Budget
      Releasing the Project for Execution
      Confirming the Activities
      Checking the Actual Dates
      Entering Activity Allocation
      Evaluating the Project
      Storing the Settlement Rule
      Executing the Settlement
   Make-To-Order Production of Elevators
      Additional Information: Assembly Processing Using Projects
      Basic Data and Settings
         Data Used During This Process
         Standard Work Breakdown Structure
         Standard Network
         Network Parameters from the Sales Order
         Configuration Profile
         Characteristics for Configurable Material
         Display Dependencies
      Sales and Distribution
         Data Used During This Process
         Creating a Sales Order
         Displaying Project Data
         Revenue Planning
         Confirmation
         Design Worklist
         Releasing the Project
         Partial Billing
      Design
         Data Used During This Process
         Planning Resources
         Assigning Purchase Info Records and Vendors
         Ordering Critical Components in Advance
         Processing Design Activities
      Procurement
         Additional Information for this Example
         Assigning Vendors
         Creating Purchase Orders
         Material Requirements Planning
         Monitoring Production and Procurement
         Posting the Goods Receipt
         Settling the Goods Receipt
         Confirming the Production Order
         Assembling Deliveries
         Posting the Goods Issue
         Entering Working Times
      Assembly
         Confirmation Using The Internet
   Period-End Closing for a Customer Project
      Data Used During This Process
      Calculating Overhead Rates
      Evaluating Project Data by Cost Element
      Generating the Settlement Rule
      Checking the Settlement Rule
      Executing Results Analysis
      Executing the Settlement
      Displaying the Line Items
   Project Documents in the Intranet
      Data Used During This Process
      Displaying Project Documents
   Invoicing a Project with Down Payment Processing
      Additional Process Information
      Data Used During This Process
      Creating Sales Orders and Projects
      Releasing a Project
      Confirming Activity
      Creating Down Payment Requests
      Posting Down Payments
      Confirming Activity
      Creating Invoices
      Displaying Single Line Items
      Confirming Activity
      Creating Invoices
   Engineer-to-Order with Planning of Production Lots (SEIBAN)
      Additional Process Information
      Data Used During This Process
      Displaying a Change Number
      Displaying the Material BOM
      Creating a Production Lot
      Creating a Planned Independent Requirement
      Changing the Planned Independent Requirement
      Creating a Cost Estimate for the Production Lot
      Activating the Cost Estimate for the Production Lot
      Executing MRP for the Production Lot
      Creating a Sales Order
      Releasing the Project Definition
      Assigning the Production Lot to the Network Reservation
      Processing the Planned Orders and Production Orders
      Assigning the Finished Product
   Repetitive Manufacturing with Planning of Production Lots (SEIBA
      Additional Process Information
      Data Used During This Process
      Creating a Production Lot
      Changing the Planning Hierarchy
      Entering the Planning Quantity in SOP
      Transferring the Planning Data to Demand Management
      Executing Project Planning for the Production Lot
      Converting the Purchase Requisition Into a Purchase Order
      Goods Receipt for the Purchase Order
      Creating the Pull List
      Confirming the Production