Procedure documentation Excluding Products from Planning in SAP R/3  Locate the document in its SAP Library structure

Use

If you want to plan products in SAP APO, you must exclude these products from the material requirements planning in SAP R/3. You must ensure that customer requirements are created for these products.

Procedure

  1. Create a corresponding MRP type in SAP R/3.
    1. To do this, choose Master data Check MRP types in the customizing for material requirements planning and select New entries.
    2. Enter X (without MRP, with BOM explosion) in the MRP procedure field.
  1. Assign the products to be planned in SAP APO to this MRP type in the SAP R/3 material master.
  1. Ensure that customer requirements are created for the products in SAP R/3 that you have excluded from the planning in SAP R/3. You have the following options:

Caution

The disadvantage of this option is that customer requirements are now created for products in all systems, not only for the products that are not planned in SAP R/3 or SAP APO.

Note

In the SAP APO product master you must have set the Poss. individual customer requirement indicator for the product.