Transferring Values From Cost Planning as Budget 
Course Prerequisites
Budget allocation for a project or an order is generally preceded by a cost plan that provides the initial basis for determination and allocation of the budget. As the system enables detailed planning of project or order costs, it is relatively simple to transfer the planned values as budget.
You must first create an order or a project with a structure plan, and execute cost planning.
For more information on creating a project structure plan, see the SAP Library under Accounting ® Project System ® Structures ® Project Structure Plan (PSP) ®
Processing the Work Breakdown Structure.
For more information on cost planning for a project structure plan, see the SAP Library under Accounting ®
Controlling ®
Costs ®
Cost Planning ®
Manual Cost Planning in the Work Breakdown Structure.
Procedure for Projects

The Budgeting business transaction is allowed only on the WBS elements that are ready for input, and thus can be budgeted.
3. Use either the Period list box or Goto ® Period to choose the period that you want to budget.
|
The Plan total consists of the following |
|
|
Structure planning value (independent of cost element) |
|
|
+ |
Cost element planning value |
|
+ |
Unit costing value |
|
+ |
Value of the additive orders for a project, meaning the orders assigned to this and all lower-level WBS elements. |
|
+ |
Value of the additive networks and network activities that are assigned to this and all lower-level WBS elements. |
|
= |
Plan total |