Entering content frame

Process documentation Master Production Scheduling Procedure Locate the document in its SAP Library structure

Prerequisites

Note

You define MRP types in Customizing for MRP in the IMG activity Check MRP types.

Process Flow

  1. You start the total planning run for master schedule items or single-item planning for master schedule items.

In contrast to the MRP run, this planning run only plans the master schedule item level. The system creates dependent requirements for the BOM level directly below the planning level. However, this level and lower levels are not planned.

Depending on the settings of the MRP type, any changes to be made to the master plan are only proposed within the planning time fence. Outside of the planning time fence, procurement proposals are created as usual.

  1. You use interactive planning to check the planning result and finely tune the master plan for the master schedule items. You hereby pay particular attention to planning and scheduling the procurement proposals that are required to cover shortages within the planning time fence.
  1. Once the master plan has been finely tuned for the master schedule items, you start the total planning run for all dependent parts. Various options exist here:
  1. You evaluate the planning result using standard evaluations or user-specific evaluations.

See also:

Structure link Planning Time Fence

Structure link Firming Type

Structure link Interactive Planning

Structure link Carrying Out the Planning Run

Structure link Planning Result and Planning Situation

 

 

Leaving content frame