This graphic is explained in the accompanying text Example of Forward Scheduling for External Procurement Locate the document in its SAP Library structure

Example Data

Material shortage date

01.08 (Friday)

Planned delivery time of the material

10 days (calendar days)

Processing time for purchasing

1 day (workdays)

Goods receipt processing time

2 days (workdays)

Opening period

10 days (workdays)

Workdays = Monday to Friday, no bank holiday

 

Scheduling

  1. Material shortage date plus processing time for purchasing plan plus planned delivery time = delivery date
  2. 01.08. (Friday) plus 1 workday + 10 calendar days = 14.08. (Thursday)

  3. Delivery date plus goods receipt processing time = availability date

14.08. (Thursday) plus 2 workdays = 18.08. (Monday)

 

 