Process documentation Calculating the Provision Date for Components Locate the document in its SAP Library structure

Implementation Options

The system also calculates the provision date of the material components during lead time scheduling.

Process Flow

The materials and required quantities are determined using the BOM explosion. The provision times are calculated as follows:

Note

In Customizing for the scheduling levels, you can also set that the dependent requirement dates can be scheduled to the order start date instead of the operation start date in lead time scheduling.