Function documentation Replenishment up to Maximum Stock Level Locate the document in its SAP Library structure

Use

You use the lot-sizing procedure Replenishment up to maximum stock level if you want to fill the stock up to the highest possible level or if you can only store a certain quantity of a material due to the container size. This applies to a tank, for example. The capacity of the tank determines the maximum stock level.

Integration

Caution

You can use this lot-sizing procedure with reorder point planning or MRP.

Prerequisites

You have set the indicator HB in the Lot size field and the maximum quantity to stock in the Maximum stock level field in the material master (MRP 1 view) for the material.

Features

This graphic is explained in the accompanying text

The requirements dates are not taken into account. The system calculates the total of all requirements.

The calculation of the lot size occurs in two steps using two formulas:

Formula 1

This graphic is explained in the accompanying text

Formula 2

This graphic is explained in the accompanying text

The system creates the order proposal using the greater of the two lot sizes calculated.

The system calculates the lot size using the following formula:

This graphic is explained in the accompanying text

Example

Example Data

Maximum stock level

5.000

Reorder point

2.000

Current plant stock

1.000

Existing fixed receipt elements

None

Total requirements

4.000

Lot-Size Calculation

1. Reorder point planning without taking external requirements into account

5.000 - 1.000 = 4.000

2. Reorder point planning where external requirements are taken into account

Formula 1: 5.000 - 1.000 = 4.000

Formula 2: 2.000 + 4.000 - 1.000 = 5.000 (this value is the larger and is copied over)

3. Reorder point planning where external requirements are taken into account or MRP, maximum stock level variant 1

5.000 + 4.000 - 1.000 = 8.000

 

 