Procedure documentation Changing BOM Explosion Numbers Locate the document in its SAP Library structure

...

       1.      In the menu, choose MRP ® Master Data ® BOM Explosion Number ® Edit.

The system displays the initial screen for maintaining the BOM explosion number.

       2.      If necessary, enter certain restrictions for the selection of existing BOM explosion numbers:

¡        If you want to maintain a specific BOM explosion number, enter it in the From BOM explosion number field. This BOM explosion number is then displayed first.

¡        If you want to maintain all the BOM explosion numbers for a specific interval, enter the appropriate BOM explosion numbers in the From BOM explosion number and To BOM explosion number fields.

¡        Enter the maximum number of BOM explosion numbers to be selected in the Maximum number for selection field.

¡        if you only want to maintain the BOM explosion numbers of a certain plant, enter the appropriate plant in the Plant field.

¡        If you only want to select the BOM explosion numbers of a specific material, enter this material in the Material field.

       3.      Choose This graphic is explained in the accompanying text (Execute).

The screen for maintaining the BOM explosion numbers now appears.

       4.      Select the BOM explosion number(s) that you want to change and choose This graphic is explained in the accompanying text (Continue).

The selected BOM explosion numbers are now made ready for input.

       5.      Change the corresponding data.

       6.      Save your entries.

 

 