Deactivating (and Reactivating) a Stability Study 
Use
You can deactivate a stability study for an unspecified period of time and reactivate the study again at a later date. To do this, you use the follow-up functions Deactivate Stability Study and Activate Stability Study respectively. If you deactivate a stability study, the system responds as follows:
Procedure
The initial screen for changing a stability study appears.
The screen for changing the stability study data appears.
A dialog box appears asking you whether or not you want to cancel the stability study.
The dialog box is closed and the change screen for the stability study reappears.
Result
The testing schedule for the stability study and the stability samples for the storage conditions are locked and the status INAC (inactive) is set in the study.
You can reactivate the stability study by performing the procedure above again and executing the follow-up function Activate Stability Study (in place of Deactivate Stability Study).