Entering content frame

Function documentation Component/Schedule Line Overview Locate the document in its SAP Library structure

Use

The Component/Schedule Line Overview mainly contains data that describes the components or schedule lines (the Progress Tracking objects). The only field in which you can enter data is for the event scenario.

Features

Information Icons

Particular information about the Progress Tracking object is also displayed within the overview in the form of the following icons, for example, in the event field, depending on the processing status of the relevant object:

Icon

Icon Name

Description

Other info

This graphic is explained in the accompanying text

Initial Event Overview

Events have been assigned during the process of the current transaction but have not yet been scheduled or manually processed.

This icon is displayed in the event column (Evnt).

 

This graphic is explained in the accompanying text

Event Overview

Displayed as the alternative to the Initial Event Overview icon above.

Events are assigned to the Progress Tracking object and have already been saved once, or at least scheduled or manually processed.

This icon is displayed in the event column (Evnt).

Also displayed in the toolbar, for navigating to the displayed assignment.

This graphic is explained in the accompanying text

Subitems

Subitems exist for the Progress Tracking object.

This icon is displayed in the subitem column (SItm).

Also displayed in the toolbar, for navigating to the displayed assignment.

See Maintaining Subitems

This graphic is explained in the accompanying text

Status Note

Status information exists for the Progress Tracking object

 

This graphic is explained in the accompanying text

Documents

Document assignments exist for the Progress Tracking object from the corresponding standard transactions.

Also displayed in the toolbar, for navigating to the displayed assignment.

 

Function Icons

The following icons are also displayed in the toolbar:

Icon

Icon Name

Description

Other info

This graphic is explained in the accompanying text

Object Filter

Filter the overview according to Progress Tracking attributes

 

This graphic is explained in the accompanying text

Reset

Reset the Object Filter

 

This graphic is explained in the accompanying text

Date Mass Change

Mass change of dates of individual events for the selected Progress Tracking objects

 

This graphic is explained in the accompanying text

Scenario Mass Change

Mass change of the event scenario assignment

 

This graphic is explained in the accompanying text

Complete View

Call up the Evaluation function for the selected Progress Tracking objects

See Evaluation of Progress Tracking Data

This graphic is explained in the accompanying text

Send Message to Requester

Inform someone via mail with an executable work item for displaying the Progress Tracking for the selected Progress Tracking object

 

This graphic is explained in the accompanying text

E-Mail

Send an e-mail

 

 

Activities

Assigning an Event Scenario

The event scenario field is the only field in the Component/Schedule Line Overview into which you can enter data. There are three different ways of assigning a scenario:

For more information, see Assigning an Event Scenario.

Filtering According to Progress Tracking Data

Using the This graphic is explained in the accompanying text Object Filter, you can filter the overview of Progress Tracking objects according to the Progress Tracking data. You can:

Mass Change to Dates of an Event

When you choose This graphic is explained in the accompanying text Date Mass Change you can change one or more dates of an event for the selected Progress Tracking object. You can also carry out mass initialization, which means that the dates in question are set to zero and thereby deleted.

Note 

Fixed dates are excluded from the mass change function.

Mass Change Scenario

The mass change scenario function enables you to set new event scenario assignments and overwrite existing assignments for one or more Progress Tracking objects. You select the Progress Tracking objects, choose This graphic is explained in the accompanying text Scenario Mass Change and select the scenario you require. This scenario is then assigned to all the selected Progress Tracking objects. If you overwrite an existing scenario those events that are not assigned to the new scenario are automatically deleted. Manually assigned events are also deleted.

Hotspots

If an individual data field is underlined, this means that a hotspot has been defined for this field. To branch to the display of the master data for the relevant field, click the underlined data once.

Leaving content frame