We will look at how dynamic selections work in a sample project, called WBS-A.

This graphic is explained in the accompanying text

Example 1

You select the project WBS-A taking account of the dynamic selections entered for project manager Morris. They are maintained for the project and WBS elements. You have activated Dynamic sels and Incl.hierarchy in the database profile.

As a result, the project reports are presented as follows:

Description

Level

Responsible person

WBS-A

0

Morris

WBS-A-1

1

Morris

WBS-A-1-1-1

2

Morris

WBS-A-1-1-1-1

3

Morris

 

The costs for WBS element WBS-A-1-1 and WBS-A-1-1-1-2 are not totaled up to WBS element WBS-A-1.

Example 2

Deactivate the Dynamic sels in the database profile; the subordinate WBS elements are included in the selection. The costs are totaled up.

As a result, the project reports are presented as follows:

Description

Level

Responsible person

WBS-A

0

Morris

WBS-A-1

1

Morris

WBS-A-1-1

2

Smith

WBS-A-1-1-1

3

Morris

WBS-A-1-1-1-1

4

Morris

WBS-A-1-1-1-2

4

Smith

 

 

 

 

 

 

 

 