Function documentation Dates in the Work Breakdown Structure (WBS) Locate the document in its SAP Library structure

Use

You can plan dates for individual WBS elements as soon as you have entered the outline dates for your project in the project definition. In rough-cut planning, you specify dates for WBS elements that are binding for more detailed planning. You can then use this rough-cut plan as the basis for more detailed planning or scheduling using networks ( see Network Scheduling). You can use several functions in date planning, to compare, reconcile, or calculate dates at a later point in time.

Features

At work breakdown structure level you can:

Furthermore you can carry WBS scheduling , in which you schedule a project or sub-hierarchy with all its assigned activities.