Procedure documentation Completing Transportation Planning Locate the document in its SAP Library structure

Procedure

To complete transportation planning for a shipment document, first access the document either using the change function or using a worklist for transportation planning (see Processing Shipment Documents).

After you have completed all the necessary activities, such as packing, maintaining texts, or assigning service providers, you can set the Planned status in the shipment header screen. For more information on setting this status, see Maintaining Status in the Shipment Document. Once the Planned status has been set, leg determination is performed automatically. The shipment document is then ready for shipment completion.

Result

Setting the Planned indicator in the header screen of a shipment document will result in the following:

· You can no longer add deliveries to the shipment document.

· You cannot move deliveries within the shipment document.

· You cannot remove deliveries in the shipment document.

· You cannot reassign deliveries to other shipment documents in the transportation planning work list.

· You can copy the route from the deliveries into the shipment header if the appropriate indicator is set in the shipment type and if all deliveries in the shipment document have the same route.

· You can copy the forwarding agent from the deliveries as the transportation service agent in the shipment header. However, the indicator for copying the forwarding agent must first be set in the shipment type and all deliveries must have the same forwarding agent.

 

 

 

 