!--a11y-->
Use
If you want to schedule planned orders on the basis of
production rates and takt times, use the planning table with Sequencing.Sequencing is a production line-oriented, graphic tool that schedules the planned orders you create in the planning table or that were created in the planning run and then sequences them according to a predefined process.
As the planned orders dispatched in Sequencing are automatically firmed, you should only use Sequencing in the short-term period.
Prerequisites
If this unit of measure deviates from the material’s unit of measure, you must specify the line hierarchy’s unit of measure and the conversion factor in the material master record, under Extras
Sequencing.
Features
In this case, the system uses the production rate and number of takts you entered manually to schedule the planned orders in Sequencing. The advantage here is that you do not have to maintain a rate routing. You only have to create a line hierarchy for the production line.
In this case, the system uses the production rate determined in line balancing in Line Design and the number of takts for scheduling. Here, you have to maintain a line hierarchy and a rate routing and you also have to carry out line balancing.