Function documentation Planning Table and Capacity Planning Locate the document in its SAP Library structure

Use

You can also use the planning table with Capacity Planning.

Here, the system first carries out lead time scheduling using the routing defined in the production version.

Depending on your settings, the system creates either detailed or rate-based capacity requirements and displays these in the planning table.

Prerequisites

Customizing

You must check the scheduling parameters in Customizing for MRP or for Repetitive Manufacturing under Define Scheduling Parameters for Planned Orders.

Master data

Initial screen of the planning table

Features

The system displays the capacity data for the selected lines in the upper section of the planning table. For each capacity category of a production line, you can instruct the system to display the capacity requirements, the available capacity and the capacity load.

For more information, see: Capacity Planning in the Planning Table

From the REM planning table, you can branch to the capacity planning table. For more information, see: Working with the Capacity Planning Table

 