!--a11y-->
Example: Static ECO Connected to Zone

The static ECOs defined for a site include the following combinations of constraint objects:
|
ECO |
Zone |
Combination |
Resource Types |
|
1 |
ZN04 |
1 |
1 x Picker; 1 x Simple Forklift |
|
2 |
4 x Pickers |
||
|
2 |
ZN06 |
1 |
2 x Pickers; 1 x Simple Forklift |
|
2 |
5 x Pickers |
Marcus Adams, a
picker, selects a system-guided task using his presentation device. One of the
tasks he is capable of doing involves moving materials from zone ZN04 to zone
ZN06. 
There are currently 4 pickers subscribed to the destination zone ZN06 so ECO 2 is available. However, since the source zone ZN04 has reached its capacity of 4 pickers, ECO 1 is unavailable. Since the movement task is subscribed to an unavailable ECO, it cannot be assigned to Marcus.