Use
You complete the initial test by making the usage decision for the inspection lot. This usage decision determines whether or not the stability study will be continued. When you make the usage decision, you can choose between the following usage decision codes:
If you choose and save this usage decision, the system automatically executes a follow-up action that sets the user status Initial Test Completed in the stability study.
If you choose and save this usage decision, the system also executes a follow-up action automatically that sets the user status Initial Test Completed in the stability study. Furthermore, the system will branch to the stability study in the change mode as soon as you have saved the usage decision. In this way, you can manually trigger additional follow-up functions in the action box (for example, to cancel or complete the stability study, to print lists, and so on).

The usage decision codes and corresponding follow-up functions described above are examples provided by SAP in the delivery system.
If necessary, you can define your own:
Selected sets with usage decision codes for the initial test
If you choose to do this, it is important that the status Initial Test Completed is set in the stability study, when the usage decision is made. If the system cannot set this status by means of the follow-up action for the usage decision (for example, because the stability study is currently being processed by another user and is locked), you can set this status manually in the stability study by executing a corresponding follow-up function in the action box.
Prerequisites
You have recorded inspection results for all characteristics, valuated and closed all characteristics, and saved the inspection results.
Procedure
The initial screen for recording the usage decision appears.
The screen for recording the usage decision appears.
See also:
Making a Usage Decision
Result
The inspection lot for the initial test has been completed.
If you made the usage decision to: