!--a11y-->
Manually Assigning Tasks to Resources 
Use
You can manually assign one or more
tasks to a resource via the TRM Monitor.Prerequisites
You can only assign tasks with the status of 01 Available.
Procedure
|
ALV |
Hierarchy Tree |
|
|
|
|
The Assign Tasks to Resource dialog box appears, displaying the selected tasks and suitably qualified resources. |
The Assign Tasks to Resource dialog box appears, displaying the selected tasks and suitably qualified resources. |
|
|
|
|
Result
The tasks are given the status of 03 Accepted and the TRM Monitor display is updated accordingly.
The tasks are assigned to the resource and are displayed on the resource’s presentation device when it selects the next system-guided task.

You can also manually un-assign from resources tasks with the status of 03 Accepted.