Scheduling with Service/Maintenance Orders 
Use
Use this function to take maintenance orders and service orders, which are included as subnetworks in a network, into account during WBS scheduling and overall network scheduling.
Features
In WBS scheduling and overall network scheduling you can specify in the To schedule field on the Basic dates screen which objects the system schedules:
During scheduling of networks together with maintenance/service orders, the system first only schedules the networks. .
The dates determined for the activities are then copied to the headers of the maintenance and service orders, which are then scheduled with these outline dates.
If errors occur during scheduling of maintenance or service orders, they are recorded in the scheduling log.
See also:
Scheduling Projects with Maintenance / Service Orders