!--a11y-->
Multiperiod Consolidation with a Consolidation Cycle 
Use
If you want to consolidate across more than one period, use multiperiod consolidation.
Integration
A consolidation cycle for multiperiod consolidation applies to a particular
version.Prerequisites
You have made the following settings in Customizing for Consolidation under Data ® Data Monitor ® Consolidation Cycle for Multi-Period Consolidation or Consolidation Functions ® Consolidation Monitor ® Consolidation Cycle for Multi-Period Consolidation:
Features
Multiperiod consolidation provides the following features:

In the data monitor and the consolidation monitor, the status display does not necessarily apply to multiple periods:
Within a consolidation cycle, you can execute tasks of a period while one or more tasks in the prior period are not yet blocked.

However, you should make sure that the tasks of the prior period are blocked.
Examples
Example 1
In Customizing for the consolidation cycle, you have defined a consolidation cycle with one delta year:
|
Consolidation cycle |
CC1 |
|
Assigned version |
100 |
|
Start period |
012 |
|
Start year |
2000 |
|
Delta year |
02 |
|
Consolidation frequency |
4 (quarterly: periods 003, 006, 009, and 012) |
The consolidation cycle therefore begins in period 012/2000.
Additional periods of the consolidation cycle:
The above-mentioned functions are available during the consolidation cycle (for example, you can scroll between periods in the data monitor and in the consolidation monitor).
Example 2
In Customizing for the consolidation cycle, you have defined a consolidation cycle with two delta years:
|
Consolidation cycle |
CC2 |
||
|
Assigned version |
200 |
||
|
Start period |
012 |
||
|
Start year |
2000 |
||
|
Delta year |
02 |
Consolidation frequency |
4 (quarterly: periods 003, 006, 009, and 012) |
|
Delta year |
04 |
Consolidation frequency |
2 (semi-annually: periods 006 and 012) |
The consolidation cycle begins in period 012/2000.
Additional periods of the consolidation cycle: