Creating a Simulation Version by Copying from 
Procedure
Choose Logistics/Accounting
®
Project management
®
Planning.(The same functions are also in the Operative structures menu under Work breakdown structure).
Choose Project
®
Simulation
®
Create.
Enter the
simulation version key, the project definition key and the project profile.
Enter the required source. This could be:
- a project definition
- a project definition and a version key.
- a standard project definition
- If necessary set the With activities indicator.
- Choose Continue.
The source structure is copied into the new simulation version and the
project planning board appears
- Save the simulation version.