Making Individual Confirmations 
Entering Confirmation Data
The Create Network Confirmation: Actual data screen appears.

It is also possible to call up the transaction directly from the
Project Builder and the project planning board.Entering Dates, Duration, and Work
If you enter both an actual start and an actual finish date , the system automatically calculates the actual duration. You can also enter an actual duration without entering actual dates. In both cases the actual duration is only saved in the confirmation slip. When entering the actual work, you enter the amount of work done since the last confirmation. When you save the confirmation, the value you have entered is added to the existing actual work. For more information see
Calculation of Actual Dates and Actual Work, Remaining Work and the Degree of Processing.Confirming Business Processes
If you use
activity-based costing, you can confirm business processes. You enter the business process, the activity with unit to confirm, and if required, the remaining activity to be carried out.
Goods Movements
For details of how to process goods movement in confirmation, see
Goods Movements
Parameters for Confirmations
You can change some of the Customizing settings directly in the application. To do so, choose Parameters on the Initial screen or the Activity overview .
Primarily you can change the default settings such as: