Use
The system executes this function automatically, when you save a confirmation.
Features
The system copies the actual dates from your confirmation to the network or to the WBS element to which the confirmed activity is assigned.
The start and finish dates, on which processing began or finished, are used to calculate the actual dates.

Actual duration is only used in reports and evaluations. Actual duration is not copied into the activity and does not effect capacity load or actual costs (see
Activities
If you make more than one confirmation for an activity, the system copies the following dates into the network:
If an activity is assigned to a WBS element, the actual dates are copied into the WBS element as follows: