Procedure documentation Creating a Delivery from a Project Locate the document in its SAP Library structure

Procedure

  1. Choose Logistics or Accounting ® Project System ® Material ® Execution ® Delivery from project.

An entry screen appears.

  1. Enter the selection and filter criteria for the material components that you want to deliver.

Note

Selection via a project definition automatically excludes simultaneous selection via a sales order. You can, however, select both a WBS element and a sales order.

  1. Choose This graphic is explained in the accompanying text Components.
  2. If there are several sales order for the chosen project, a dialog box appears. Select the sales order that the general data should be copied from.

    A dialog box appears with the general data for the delivery.

  3. Check the general data that the system proposes and change or append it, if necessary. Then choose This graphic is explained in the accompanying text Copy.
  4. The system checks the availability of the selected material components on the planned goods issue date.

    A screen appears for editing the delivery items.

  5. Enter the delivery quantities for each item.

The system proposes the available open quantity is proposed as the default.

  1. Save the delivery.

Result

The system then creates the delivery documents - as many as required - if different goods recipients or different delivery dates were entered. It takes all components into account whose delivery quantity is larger than zero.

You can then display deliveries that you have created from projects in an overview.

 

 

 