Procedure documentation Scheduling Results  Locate the document in its SAP Library structure

Features

There are several ways of displaying the scheduling results:

You can display an overall overview of all the dates in WBS scheduling by choosing Extras ® Logs ® Old/new date overview.

Call up the structures information system by choosing Logistics ® Project System ® Information System ® Structures ® Structure Overview. If necessary enter a PS info profile. On the selection enter the relevant data.

You can also call up a dates report in the information system from the project planning board. Choose Extras ® Run dates report. A dialog box appears, in which you can select the objects for which you want to run the report.

To add new fields to the overview, choose Change display variant and select the required fields.

In the network header, the scheduled start and the scheduled finish for the whole network are displayed.

The activity dates are displayed on the Dates tab page of the activity detail screen.

The figure demonstrates how the activity dates are displayed in the network structure graphic. This graphic is explained in the accompanying text

Note

If errors occur during scheduling, a scheduling log is created automatically. For more information, see Error Log.

 

 