Maintaining Data For Scheduling 
Where Can You Maintain Data for Scheduling?
You maintain... |
In the following tab page |
normal/minimum duration for internal activities |
Internal |
duration for general costs activities |
Costs |
duration for external activities |
Internal |
Constraints |
Dates |
Indicator: Earliest/latest |
Dates |
reduction strategy for internal activities |
Internal |

You enter the offset to start and finish for activity elements on the detail screens for work and general costs, and on the overview screen for external elements.
Starting Scheduling
To start scheduling, proceed as follows:
or Edit Scheduling is started.
Changing Scheduling Parameters
You can change some of the settings that you make in Customizing for scheduling in the applications by choosing Settings
® Options in the project planning board, Settings ® Scheduling parameters (networks) in the Project Builder, or Edit ® Settings ® Scheduling parameters in network maintenance. In the Project Builder you must have selected a network object for the menu to be active.See also:
Settings for Scheduling Parameters