Scheduling of Finally/Partially Confirmed Activities 
Features
If you schedule a network that has activities with final and partial confirmations, the system schedules as follows.
The earliest finish date is equal to the actual start date plus the forecast processing time. If you have entered a forecast finish date in the confirmation, scheduling takes the forecast finish date as the earliest finish date. If neither a forecast duration nor a forecast finish date exists, the system then proceeds from the planned duration (basic dates) and adds it to the actual start date.
For the latest start and finish dates, the activities from the start date of the successor are scheduled backwards so that the floats can be calculated for the activity.
If you set the Shift network indicator in the scheduling parameters, you determine whether the actual dates of partially confirmed activities are taken into account. The system schedules using the remaining duration of the activities and starts with the earliest start date of the activities that it has calculated.