Function documentation Network Scheduling Locate the document in its SAP Library structure

Use

Scheduling determines the earliest and latest start and finish dates for carrying out activities in the network and calculates the required capacity requirements as well as the slack time or "floats".

Features

What is Scheduled?

The following are scheduled:

When is Scheduling Carried Out?

A network is scheduled:

If you release the network, the indicator is set automatically and the network is scheduled each time you save it.

If you make changes in the network which are relevant to scheduling, the system automatically sets the status "Dates are not updated" (NTUP).

Which Set of Dates is Used in Scheduling?

In the network, you can enter basic and forecast data for dates, duration, units, constraints and work. For scheduling, you specify in the network header, with which set of dates scheduling is to be carried out. In network maintenance choose Edit ® Settings ® Set of dates and then either Basic or Forecast. In the project planning board choose Settings ® Options, in the dialog screen the Planning board node and on the Settings tab page the relevant set of dates.

For more information on the various dates in the Project System, refer to Types of Dates.

Scheduling Results

The system determines the following dates:

See also:

Maintaining Data for Scheduling

 