Scheduling the Overall Network 
Definition
In a complex project, different networks can exist for substructures. The dependencies in a project can make the activities in one network dependent on the completion of activities in another network. You can use the function for scheduling the entire network to take these dependencies into account during the calculation of dates.
In overall network scheduling, the system then schedules all networks that are linked with relationships.

Procedure
In the SAP Easy Access menu choose Logistics ® Project System
® Dates ® Overall network scheduling.Enter the network that is to be scheduled.
On the initial screen for overall network scheduling you can determine the scheduling type (backwards/forwards) and whether service/maintenance orders are taken into account.