Scheduling the Work Breakdown Structure 
Use
You can schedule a project or a sub-hierarchy of the project with all activities assigned to it.
Procedure
The initial screen for WBS scheduling appears on which you enter the relevant data.
What do you want to do? |
Action |
Maintain dates for the whole project |
Enter the project definition. |
Maintain dates for a subhierarchy or a WBS element |
Enter the WBS element. |
Select all the activities assigned to the WBS elements |
Set the With activities indicator. |
If there is not a basic start date for activities or WBS elements, a dialog box is displayed.

Errors in scheduling are displayed in the error log.
. All dates in the project are saved.
You can display an overall overview of all the dates in WBS scheduling by choosing Extras ® Log ® Old/new date overview.