Use
The following table presents the general functions available in dates scheduling. You can call them up in all dates scheduling transactions by clicking on the relevant icon or in the Edit menu.

The functions are valid for all sets of dates. If the function is inactive, that means it is not valid for that particular set of dates.
Features
Function |
Icon/Menu Path |
What You Should Know |
Schedule |
Choose |
You start WBS scheduling. |
Shift Dates |
Choose Edit ® Shift dates ®
|
You can enter a new start or finish date for a project, a subtree or a WBS element. You can use the shift dates function for both basic and forecast dates, regardless of planning method. |
Comparing Dates |
Choose |
Use the compare dates function to compare the various types, for example basic dates with forecast dates. You can use the Compare dates function for all sets of dates regardless of planning method. |
Reconciling Dates |
Choose Edit ® Reconcile dates ® |
|
|
The scheduled dates from network scheduling are copied to the WBS elements as basic or forecast dates. For information about copying actual dates, see Copying Actual Dates from Confirmations to WBS Elements | |
|
You can transfer the dates from one WBS element to all subordinate WBS elements. You can carry out this function for all sets of dates, regardless of planning method. | |
|
You can transfer the dates from one WBS element to all superior WBS elements, if these higher-level WBS elements do not yet have any dates. You can carry out this function for all sets of dates, regardless of planning method. | |
|
The basic dates are transferred to the forecast dates and vice versa. | |
Checking Dates |
Choose Edit ® Check dates ® |
|
|
The system checks whether the basic or forecast dates of the WBS element lie within the time frame of the superior WBS elements. | |
|
The system checks whether the basic or forecast dates of the activities lie within the time frame of the WBS element to which they are assigned. | |
|
The system checks whether the scheduled dates of the WBS element lie within the time frame of the superior WBS elements. | |
|
Makes a final confirmation for the selected WBS element. | |
For actual dates, you can only use the Final confirmation WBS function in the Check Dates menu entry. The system does not check whether the dates lie within the framework of the project definition. | ||

You can also change dates in the project planning board.. To do so, in the graphic move the date bar for the relevant WBS element or activity.