Planning Basic and Forecast Dates 
The initial screen for time scheduling is displayed.
What do you want to do? |
Action |
Maintain dates for the whole project |
Enter the project definition. |
Maintain dates for a subhierarchy or a WBS element |
Enter the WBS element. |
Select all the activities assigned to the WBS elements |
Set the With activities indicator. |
Enlarge your screen so that you can see all the data. On the right of the table you see the indicators Ac and Sd.
To update the scheduled dates for the WBS element, you must reschedule using the WBS scheduling function.
The system checks the dates against the factory calendar and calculates the duration.
If the specified dates are later than the dates of the superior WBS element or the project definition in top-down planning, a warning is issued.
If you want to maintain other dates or basic data, you can use the relevant tab pages to go to the relevant screens.
The system checks the dates when saving. If there are schedule conflicts, you must adjust the dates.