Procedure documentation Determining Planned Costs in Networks Locate the document in its SAP Library structure

Prerequisite

Depending on what settings you have entered in the network header control data, the system automatically calculates the planned costs:

Regardless of this, you can determine the planned costs at any time, using network maintenance.

Procedure

  1. Choose Logistics or Accounting ® Project System ® Basic Data ® Project ® Special Maintenance Functions ® Network ® Change.

This brings you to the initial screen for changing networks.

  1. Enter the relevant data and choose This graphic is explained in the accompanying text.
  2. The Change Network: Header Data screen appears.

  3. Choose This graphic is explained in the accompanying text.

The system determines the costs:

Result

The system calculates the current planned costs for the network. If errors occur, the system directs your attention to the error log . You can evaluate the result of the costing directly from the network.

See Displaying Planned Costs.

 