Assigning PRTs
to Activities 
· You can only assign PRTs with material master records if:
- The Prod. resources/tools view has been maintained in the material master
- the MM/PP status of the material permits assignment
· You can only allocate PRTs with a PRT master record (miscellaneous) if the PRT status permits usage planning of the PRT.
· You can only plan the usage of PRTs with document info records when they have the released for production status.
· You can only allocate PRTs with an equipment master record, if the Production resource/tool view has been maintained in the equipment master record.
...
1. Call up a network or standard network in create or change mode.
2. Choose Goto ® Activity overview.
3. Select the activities to which you want to assign PRTs.
4. Choose Activity ® PRT overview.
- If no PRT has yet been assigned to the activity, the PRT New Entries screen appears.
- If PRTs have already been assigned, the PRT overview screen appears.
To assign another PRT, choose Edit ® Object ® New Entries and then the PRT category.
5. Enter the relevant data on the detail screen.
6. Choose Back.
The PRT is allocated to the activity.
7. Save your data.
You can maintain more data for the PRT by choosing Details ® PRT ® General.
If you have not entered any default values for the PRT, you can maintain an offset to the start or finish by choosing Details ® PRT ® Dates.
If you have not entered default values, you can maintain formulas for the quantity and usage value (only in networks) by choosing Details ® PRT ® Quantities.
No business processes have been defined for production resources/tools in status management. If you execute a business transaction for a network activity, the PRT also receives the relevant system status.
If you have defined a status profile for a user profile, you can enter a user status for PRTs by choosing Prod resources/tools ® Status.