Use
To be able to access additional project reports from a report, you must designate the relevant reports as receiver reports when you define them.
You do this by means of the report-report interface. For more information, see the information system section of the Project System IMG.
Prerequisite
You assign the receiver reports when you create them, or when you later change them. To do the latter, you must access the change mode of a subobject from the report - for example, choose characteristics.
Procedure
The Assign Reports dialog box appears, showing a list of the existing hierarchy reports.
The system displays the dialog box Enter Application Class. The field contains the abbreviation PS for projects.
The Specify Report Type dialog box is displayed.
The system displays the dialog box Add Drilldown.
Result
When you run your report, you can branch to one of the assigned reports by choosing Goto