Conceptual documentation Assemble-to-order with Projects Locate the document in its SAP Library structure

Use networks and projects for assemble-to-order if you manufacture or engineer your products to order and you are not sure exactly how you are going to execute the sales order:

Note

You can still use planned orders and production orders if you choose to create a network from a sales order.

Account Assignment

In assemble-to-order with projects you can choose where the costs are collected: for example, in a work breakdown structure element (WBS element), in the sales order, or in the network.

 

Network is...

Account assignment is made to...

The standard WBS element from the standard network header...

header-assigned

sales order

is not copied into the network header

activity-assigned

project

is copied into the network header as a WBS element.

If no standard WBS element has been entered in the standard network header, you have to specify a WBS element when you save.

header-assigned

project

is copied into the network header as a WBS element.

If no standard WBS element has been entered in the standard network header, you have to specify a WBS element when you save.

Note

It is not possible to assign an network with activity account assignment to a sales order.