Entering content frame

Procedure documentation Copying Actual Dates from Confirmations to WBS Elements Locate the document in its SAP Library structure

Use

You can copy actual dates from activity confirmations to the superior WBS elements and use these dates as provisional actual start and finish dates.

Procedure

  1. Choose Logistics/Accounting ® Project System ® Dates ® Change WBS dates.
  2. Enter a project definition or a WBS element.
  3. Choose Edit ® Reconcile dates ® Determine actual dates.

Result

The provisional actual start or finish dates are copied to the corresponding fields in the table area.

Leaving content frame