Procedure documentation Completing a Stability Study Locate the document in its SAP Library structure

Use

When you complete a stability study, you bring the study to a close (typically after all stability tests have been performed as originally planned). The system then responds as follows:

You can only complete a stability study once.

Prerequisites

You can only complete a stability study if no open test dates are pending in the testing schedule (for example, dates that have not been called, confirmed, or skipped).

Procedure

  1. From the SAP Easy Access menu, choose Logistics ® Quality Management ® Stability Study ® Stability Study ® Change.
  2. The initial screen for changing a stability study appears.

  3. On the initial screen, enter the key of the stability study you want to process and then choose Enter.
  4. The screen for changing the stability study data appears.

  5. In the action box on the right side of the screen, choose the follow-up function Complete Stability Study.

A dialog box appears asking you whether or not you want to complete the stability study.

  1. Choose Yes.

The dialog box is closed and the change screen for the stability study reappears.

Result

The testing schedule and all physical samples belonging to the stability study are locked and the status COMP is set in the stability study. All inspection lots created for the study that are:

As a final step, you can print out the storage removal list for all stability samples and remove the stability samples by means of a follow-up function in the stability study, or you can create reserve samples.