!--a11y-->
Customizing Settings: Download 
Before you use the Production Optimization Interface, you must make several settings in Customizing.
You will find specific instructions in the implementation guide (IMG), Logistics General® Supply Chain Planning Interfaces ® Production Optimization Interface ®
· ALE Settings for POI.
· Data Transfer Parameters for POI
· Activate Change Pointers
In ALE settings you define the logical system and communication.
Logical System: Activities: |
Notes: |
·
Maintain logical
system · Assign logical system to client (for SAP system only)(Cross-Application Components ® Distribution (ALE) ® Basic configuration ® Set up logical system ® Allocate logical system to the client) |
The logical system is used on the selection screen for entering the target optimization systems. You can use as many logical systems as you like for a physical optimization system. Set up a logical system for the SAP system if it does not already have one, and assign it to a client. The external logical optimization system is not assigned to a client |
Communication: Activities |
Notes: |
·
Define RFC
destination |
Standard settings for POI: ALE destination
RFC destination SAP system ® external system Connection type T |
·
Define port for RFC
destination |
Standard settings for POI: Port: <generated automatically> |
·
Reduce interim
structures for IDocs: |
For each logical system and each basic message type (for example, LOIBOM), a unique message type has to be defined by reducing the original one (for example, MYBOM). A list of the IDocs used with POI is included in the section IDocs. You can also activate the writing of change pointers for reduced message types in this step. If you reduce a message type, only the obligatory fields are automatically selected. You must select those segments and fields you want to have transferred. Fields that have not been selected for transfer always contain the value “/”. |
·
Maintain partner
profile |
Standard settings for POI: Partner number: <external logical system> Each of the message types of the customer distribution model (see above) must be assigned to the partner profile. Enter the receiver port (see above), package size, output mode and IDoc type in the detail screen of the receiver port. You must also define whether the IDocs should be sent immediately, or if they should be collected first. |
·
Maintain customer
distribution model directly |
First define a customer model for a logical SAP system. The displayed list shows which logical system is the sender and all the possible receiving systems that have been defined. "Create message type" defines which logical system receives information from the logical SAP system. When maintaining the customer distribution model, you usually add all (reduced) message types that should be sent from the SAP system to the external system. |
You must make the following settings in Customizing to enable a data exchange between the SAP system and an optimization system:
· Filter for task list usage
· Filter for task list status
· Filter for bill of material usage
· Filter for bill of material status
· Available capacity version
· Filter for production/process orders
· Filter for control keys
· Procedure to search for planned orders by work centers
Before you can download data, you must activate the writing of change pointers in Customizing:
· Activate change pointers in general
· Activate change pointers for message types (ONLY in exceptional situations in which you use message types that are not reduced). If you are using reduced message types, as recommended, you can activate them at the same time you reduce them.

Turn change pointers on or off in SCPI ® POI ® Data Transfer Parameters for POI ® Define general settings for data transfer parameters