Entering content frame

Procedure documentation Transferring Material from Individual Project Stock to Plant Stock Locate the document in its SAP Library structure

Use

The transfer posting of materials, after completing the production of individual project stock of the production lot, to plant stock is only necessary for Production lots with transfer posting.

Procedure

  1. Starting from the Inventory Management menu, choose the Reposting function key.
  2. The Enter transfer posting: Initial screen appears.

  3. Enter the movement type 411 (Transfer posting project to own) and the special stock indicator Q as well as the plant.
  4. Choose Enter.
  5. The Enter transfer posting: Initial screen appears.

  6. Enter the necessary data, for example, like material, quantity. Enter the production lot number in the WBS element field.
  7. Save your data.

Result

The materials are transferred from individual project stock to the plant stock.
Every sales order or, in the case of assemblies with the material type HALB, every production order, can use the materials from the plant stock to meet their requirements.

The planned independent requirements of the material that were created for the production lot are reduced as a result of this transfer posting.

 

Leaving content frame