Transferring Material from Individual Project Stock to Plant Stock 
Use
The transfer posting of materials, after completing the production of individual project stock of the production lot, to plant stock is only necessary for Production lots with transfer posting.
Procedure
The Enter transfer posting: Initial screen appears.
The Enter transfer posting: Initial screen appears.
Result
The materials are transferred from individual project stock to the plant stock.
Every sales order or, in the case of assemblies with the material type HALB, every production order, can use the materials from the plant stock to meet their requirements.
The planned independent requirements of the material that were created for the production lot are reduced as a result of this transfer posting.