Calling Up the DS Planning Board in Order Processing

Use

With the two differently configured detailed scheduling planning boards (DS planning boards) that you can call up in order processing, you plan in the environment of the order that you are currently processing.

In order processing and the DS planning board that you call up in order processing, you perform simulative planning - in a similar way to the directly called DS planning board - on the basis of the planning version for which you have called up order processing. In contrast to the directly called DS planning board, you cannot explicitly save the simulation version in order processing for further processing at a later date if required. If you exit and save order processing, you also copy the changes that you have performed in the DS planning board for the schedule to the planning version.

Procedure

  1. If necessary, choose the profile, with which you wish to call up the DS planning board in order processing, under Settings and Settings ® User settings on the Profile tab page.
  2. For more information, see profile maintenance.

  3. Choose Context in the order processing view.
  4. Choose the tab with the desired DS planning board.
  5. Only some of the functions and settings options are available for the DS planning board on the tab page that you call up using planning board.

  6. To call up the DS planning board with full planning board functionality, choose Full screen.

Result

The system configures the DS planning board and you can analyze or edit the detailed scheduling problems. If necessary, change the setting for the planning under Settings, for example,

To return to order processing, choose Back.

For more information, see scheduling with the detailed scheduling planning board.